Suboptimal design of well leads to reduced flow rate
Any issue leading to an actual well production below the targeted flow rate, including wrong well shape and resource underestimation.
Informations
Category: Risks due to internal deficiencies
Id: C-2
Phases:
Drilling / Testing
Consequences:
Economic / Performance / Acceptability
Mitigation
Prevention:
Select experienced staff for well design
Corrective measures:
Drill a new well
More information is available on the project deliverable
(link),
or navigate on the online version.
The colors represent a computation of typical percentage of answers expected for each cell in the risk matrix. The numbers in each cell represent the actual answers from the risk survey. More details about this computation can be found