Online Risk Register

Damage to the well/reservoir while drilling or testing

Damage to the well and reservoir can be done during drilling phase, by using unsuitable drilling fluid or due to wrong estimation of drilling parameters (e.g. high pressures) or if in-situ gases are not considered. It can also result from insufficient or too powerfull well developement or stimulation during testing phase

Informations

  • Category: Risks due to internal deficiencies
  • Id: C-7
  • Phases:
    • Drilling / Testing
  • Consequences:
    • Economic / Performance / Acceptability
    • Health / Safety / Environment

Mitigation

  • Prevention:
    • Thorough preparation of Mud Program
    • Presence of experienced staff on the field when operating
  • Monitoring:
    • Monitor mud parameters, pressure
  • Corrective measures:
    • Remediation plan to repair damages

More information is available on the project deliverable (link), or navigate on the online version.

The colors represent a computation of typical percentage of answers expected for each cell in the risk matrix. The numbers in each cell represent the actual answers from the risk survey. More details about this computation can be found here. The numbers in each cell represent the actual answers from the risk survey.